DEFENDANTS REPUDIATED THE HOME-RENOVATION CONTRACT WHEN THEY SUBMITTED A PROPOSED CHANGE ORDER REQUESTING ADDITIONAL PAYMENTS AND THREATENED TO STOP WORK IF PLAINTIFFS DID NOT AGREE; THE REPUDIATION ENTITLED PLAINTIFFS TO DAMAGES FOR TOTAL BREACH (FIRST DEPT).
The First Department, reversing Supreme Court, determined defendants (Star) repudiated the home-renovation contract when they submitted a proposed change order and threatened to stop work unless paid in accordance with the change order. The repudiation entitled plaintiffs to damages for a total breach:
On January 14, 2022, Star sent plaintiffs a proposed “Change Order 11,” which sought payment of $117,200 for overhead allegedly incurred between September and December 2021 and additional monthly payments of $29,300 starting in January 2022 through the project’s conclusion. Plaintiffs refused to approve Change Order 11 and, by January 24, 2022, Star substantially ceased performing on the project. * * *
Plaintiffs are entitled to summary judgment on their breach of contract claim because they proved as a matter of law that defendants repudiated the contract. “[W]hen a party repudiates contractual duties prior to the time designated for performance and before all of the consideration has been fulfilled, the repudiation entitles the nonrepudiating party to claim damages for total breach” … . Here, the record establishes that defendants repudiated the contract by issuing a change order requesting additional payments followed by a threat to not return to the job unless plaintiffs agreed to pay the initial amount demanded, which threat was fulfilled when they abandoned the project … . Ho v Star Contrs., Inc., 2026 NY Slip Op 05908, First Dept 10-13-26
Practice Point: Here the defendants, by demanding more payments and threatening to stop work if their demands were not met, repudiated the home-renovation contract entitling plaintiffs to damages for total breach.