New York Appellate Digest
  • Home
  • About
  • Just Released
  • Update Service
  • Streamlined Research
  • CLE Courses
  • Contact
  • Menu Menu
You are here: Home1 / Architectural Malpractice
Architectural Malpractice, Negligence

THERE WAS AN “UNWARNED” THREE-FOOT DROP ON THE OTHER SIDE OF A DOOR IN A REMOTE AREA OF THE HOSPITAL; PLAINTIFF, A HOSPITAL WORKER, WAS INJURED BY THE THREE-FOOT DROP; THE ARCHITECTURAL MALPRACTICE CAUSE OF ACTION SHOULD NOT HAVE BEEN DISMISSED ON THE GROUND NO DUTY WAS OWED TO THE PLAINTIFF; THE CONSTRUCTION COMPANY JUSTIFIABLY RELIED ON THE ARCHITECT’S SPECIFICATIONS AND COULD NOT BE HELD LIABLE (FOURTH DEPT).

The Fourth Department, reversing (modifying) Supreme Court, determined the architectural malpractice cause of action should not have been dismissed. Plaintiff, a hospital maintenance groundskeeper, was injured by a three-foot drop on the other side of a door for which there were no warning signs. Although the door was in a remote area of the hospital, Supreme Court should not have concluded the defendant architectural firm (SBRA) did not owe a duty to the hospital worker who was showing the area to a coworker. The cause of action against the construction company, however, was properly dismissed because the construction company was justified in relying upon SBRA’s specifications:

… SBRA had the initial burden of establishing that it “used the degree of care in design that a reasonably prudent architect would use to avoid an unreasonable risk of harm to anyone likely to be exposed to the danger” … . Initially, we conclude that the court erred in determining that plaintiff was not an intended user of the area where the incident occurred and thus that SBRA had no duty to plaintiff with respect to the design of that area. The evidence established that plaintiff was an employee of the hospital who was using the door in its ordinary manner, i.e., to reach the location on the other side of the door while he was showing that location to a coworker. Moreover, the coworker’s deposition testimony was submitted by SBRA in support of its motion and established that there was a three-foot differential to the floor upon exiting the door and there were no warning signs, no locks on the door, and no railings. Thus, we conclude that SBRA failed to establish as a matter of law that it had no duty to plaintiff … or that it was not negligent in the design of the relevant portion of the building … . Dentico v Turner Constr. Co. & SBRA, Inc., 2022 NY Slip Op 04237, Fourth Dept 7-1-22

Practice Point: There were questions of fact about whether the architectural firm was liable for injuries caused by a three-foot drop on the other side of a door. The causes of action should not have been dismissed on the ground no duty was owed to the plaintiff. Plaintiff was a hospital worker and the door was in a remote area of the hospital. The construction company was not liable because it justifiably relied on the architectural specifications.

 

July 1, 2022
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2022-07-01 09:08:272022-07-03 09:34:52THERE WAS AN “UNWARNED” THREE-FOOT DROP ON THE OTHER SIDE OF A DOOR IN A REMOTE AREA OF THE HOSPITAL; PLAINTIFF, A HOSPITAL WORKER, WAS INJURED BY THE THREE-FOOT DROP; THE ARCHITECTURAL MALPRACTICE CAUSE OF ACTION SHOULD NOT HAVE BEEN DISMISSED ON THE GROUND NO DUTY WAS OWED TO THE PLAINTIFF; THE CONSTRUCTION COMPANY JUSTIFIABLY RELIED ON THE ARCHITECT’S SPECIFICATIONS AND COULD NOT BE HELD LIABLE (FOURTH DEPT).
Appeals, Architectural Malpractice, Contract Law

PLAINTIFF WAS A THIRD-PARTY BENEFICIARY OF THE CONTRACT WITH THE ARCHITECTS; THEREFORE THE ARCHITECTURAL MALPRACTICE ACTION ACCRUED WHEN THE CONSTRUCTION WAS COMPLETE, RENDERING THE ACTION TIME-BARRED (FOURTH DEPT).

The Fourth Department determined the architectural malpractice action accrued when the construction was complete, despite the fact that plaintiff was not a party to the contract with the architects. Therefore the action was time-barred. The court noted that Supreme Court should have settled the record on appeal by including the transcript of the motion to dismiss the complaint as well as the accompanying memorandum of law to demonstrate preservation of the issues for appeal:

Before breaking ground on the project, plaintiff entered into an agreement with an engineering firm, pursuant to which the engineering firm agreed to provide professional engineering services on the project. The engineering firm, in turn, entered into a contract with defendant, pursuant to which defendant agreed to provide professional architectural services on the project.  * * *

A claim against an architect accrues upon the completion of performance … . “This rule applies ‘no matter how a claim is characterized in the complaint’ because ‘all liability’ for defective construction ‘has its genesis in the contractual relationship of the parties’ ”  … . “Even if the plaintiff is not a party to the underlying construction contract, the claim may accrue upon completion of the construction where the plaintiff is not a ‘stranger to the contract,’ and the relationship between the plaintiff and the defendant is the ‘functional equivalent of privity’ ” … .

Despite the lack of privity between plaintiff and defendant, plaintiff was “not a stranger to the contract” … . Indeed, we conclude that plaintiff was an intended third-party beneficiary of the contract … . * * *

Because plaintiff “is not a ‘stranger to the contract,’ ” its professional malpractice cause of action accrued upon completion of performance by defendant … . Town of W. Seneca v Kideney Architects, P.C., 2020 NY Slip Op 05323, Fourth Dept 10-2-20

 

October 2, 2020
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2020-10-02 17:50:072020-10-04 08:20:47PLAINTIFF WAS A THIRD-PARTY BENEFICIARY OF THE CONTRACT WITH THE ARCHITECTS; THEREFORE THE ARCHITECTURAL MALPRACTICE ACTION ACCRUED WHEN THE CONSTRUCTION WAS COMPLETE, RENDERING THE ACTION TIME-BARRED (FOURTH DEPT).
Architectural Malpractice, Civil Procedure, Contract Law, Negligence

QUESTIONS OF FACT WHETHER THE CONTINUOUS REPRESENTATION DOCTRINE TOLLED THE STATUTE OF LIMITATIONS IN THIS ARCHITECTURAL MALPRACTICE/BREACH OF CONTRACT ACTION (SECOND DEPT).

The Second Department, reversing Supreme Court, determined there were questions of fact about whether the continuous representation doctrine tolled the statute of limitations in this architectural malpractice/breach of contract action. Defendant’s decedent was hired by plaintiff to construct a four-story condominium. Although the work was completed in 2008 there were problems getting approval by the city and new architectural services contracts were entered in 2015 and 2018. The court noted that, where a motion to dismiss pursuant to CPLR 3211 is made on statute-of-limitations grounds, a plaintiff may remedy any defects in the pleadings in an affidavit:

“[A]n action to recover damages for malpractice, other than medical, dental or podiatric malpractice, regardless of whether the underlying theory is based in contract or tort” is subject to a three-year statute of limitations (CPLR 214[6] … ). Such an action, founded upon “defective design or construction accrues upon the actual completion of the work to be performed and the consequent termination of the professional relationship” … . However, “a professional malpractice cause of action asserted against an architect or engineer may be tolled under the continuous representation’ doctrine if the plaintiff shows its reliance upon a continued course of services related to the original professional services provided” … . * * *

Even if the defendant had met her prima facie burden, the plaintiff raised a question of fact as to whether the continuous representation toll applied. Specifically, the plaintiff averred in an affidavit in opposition to the motion that [defendant’s decedent] continued to work on the project from 2008 through the time that the parties entered into the 2015 agreement, including by continuing to revise the plans so as to subdivide the property, regularly meeting with the plaintiff, renewing building permits with the plaintiff, meeting with a “commissioner” at the DOB [NYC Department of Buildings] to discuss revised plans, and filing an application concerning the project with the DOB in 2014. Anderson v Pinn, 2020 NY Slip Op 03636, Second Dept 7-1-20

 

July 1, 2020
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2020-07-01 08:48:082020-07-04 09:21:30QUESTIONS OF FACT WHETHER THE CONTINUOUS REPRESENTATION DOCTRINE TOLLED THE STATUTE OF LIMITATIONS IN THIS ARCHITECTURAL MALPRACTICE/BREACH OF CONTRACT ACTION (SECOND DEPT).
Architectural Malpractice, Civil Procedure, Contract Law, Negligence

THE COMPLAINT ADEQUATELY ALLEGED THE TOLLING OF THE STATUTE OF LIMITATIONS PURSUANT TO THE CONTINUOUS REPRESENTATION DOCTRINE AND THE EXISTENCE OF THE FUNCTIONAL EQUIVALENT OF PRIVITY BETWEEN PLAINTIFF AND THE DEFENDANT ARCHITECT; SUPREME COURT REVERSED (SECOND DEPT).

The Second Department, reversing Supreme Court, determined the complaint alleging architectural malpractice should not have been dismissed pursuant to CPLR 3211. Plaintiff leased the first floor of a building to operate a pizza restaurant. Plaintiff hired a contractor which in turn hired an architect for the heating, ventilation and air conditioning (HVAC) design. The gas line hookup was completed in 2014. Subsequently, in 2016, National Grid shut off the gas, alleging plaintiff was stealing gas. In 2017 the defendant architect allegedly attempted to remedy the problem with the gas line. The complaint adequately pled the statute of limitations was tolled by the continuous representation doctrine and a privity-like relationship between the plaintiff and the architect:

“The law recognizes that the supposed completion of the contemplated work does not preclude application of the continuous representation toll if inadequacies or other problems with the contemplated work timely manifest themselves after that date and the parties continue the professional relationship to remedy those problems” … . In support of its motion, the architect submitted documentary evidence which included a final invoice issued by it dated August 14, 2014, and a letter of completion issued by the New York City Department of Buildings to the architect stating that its work was completed on December 20, 2014. In opposition, the plaintiffs’ submissions, which included evidence of continuing communications between [plaintiff] and the architect, and evidence of the architect’s efforts to remedy the alleged error uncovered by National Grid regarding the gas line connection for the premises, raised a question of fact as to the application of the continuous representation doctrine and supported the denial of those branches of the architect’s motion which were pursuant to CPLR 3211(a)(1) and (5) to dismiss the amended complaint insofar as asserted against it … . Contrary to the architect’s contention, the fact that two years had elapsed between the completion of its services and its subsequent efforts to remedy the problem does not render the continuous representation doctrine inapplicable as a matter of law … .

We also reject the architect’s contention, as an alternative ground for affirmance, that dismissal of the amended complaint insofar as asserted against it was warranted pursuant to CPLR 3211(a)(1) and (7), on the ground that it was not in privity with the plaintiffs. The evidence submitted by the architect, which included a copy of the contract entered into between it and the contractor, failed to utterly refute the factual allegations supporting the plaintiffs’ contention that a relationship existed between them and the architect that was the “functional equivalent of privity” … . Creative Rest., Inc. v Dyckman Plumbing & Heating, Inc., 2020 NY Slip Op 03499, Second Dept 6-24-20

 

June 24, 2020
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2020-06-24 10:18:492020-06-26 11:33:09THE COMPLAINT ADEQUATELY ALLEGED THE TOLLING OF THE STATUTE OF LIMITATIONS PURSUANT TO THE CONTINUOUS REPRESENTATION DOCTRINE AND THE EXISTENCE OF THE FUNCTIONAL EQUIVALENT OF PRIVITY BETWEEN PLAINTIFF AND THE DEFENDANT ARCHITECT; SUPREME COURT REVERSED (SECOND DEPT).
Architectural Malpractice, Negligence

ARCHITECT’S MOTION FOR SUMMARY JUDGMENT PROPERLY DENIED, THE FACT THAT ANOTHER PARTY PLACED THE ANGLE IRON WHICH INJURED PLAINTIFF IN AN EFFORT TO FIX AN ALLEGED DEFECT IN THE DESIGN OF THE SUBJECT BOILER SYSTEM DID NOT CONSTITUTE A SUPERSEDING CAUSE OF PLAINTIFF’S INJURY AS A MATTER OF LAW (FIRST DEPT).

The First Department determined defendant architect’s (Cannon’s) motion for summary judgment in this personal injury case was properly denied. Plaintiff was injured when an angle iron used to support part of a boiler system struck him on the head. Cannon argued it did not have any responsibility for the use of the angle iron as a support, which was placed there by a third party. However Cannon approved the boiler system and therefore may have been responsible for the defect which resulted in the need for the angle-iron support. Therefore the placement of the angle iron may not have been a superseding cause of the injury:

… [A]ccording to Cannon, even if it was negligent in its review of the component list or in its inspections of the ongoing work, any such negligence was not a proximate cause of the accident, because the installation of angle irons, which it never approved, and the failure of DASNY [building owner] and Martin [HVAC contractor} to heed its remediation recommendation for eight months before the accident occurred were intervening superseding causes.

“When a question of proximate cause involves an intervening act, liability turns upon whether the intervening act is a normal or foreseeable consequence of the situation created by the defendant’s negligence'” … . “The mere fact that other persons share some responsibility for plaintiff’s harm does not absolve defendant from liability because there may be more than one proximate cause of an injury'” … . Here, a jury could reasonably conclude that the effort to reinforce the cleanout port covers with angle irons was a normal and foreseeable consequence of the alleged inadequacy of the covers, which Cannon either approved or failed to detect, and which Cannon’s principal acknowledged were not the proper covers. Thus, under the circumstances presented in this case, there remain triable issues of fact as to whether, inter alia, the use of the angle iron bracing, as well as DASNY and Martin’s failure to replace the covers, despite notice from Cannon, constituted superseding causes of plaintiff’s injuries  … . Demetro v Dormitory Auth. of the State of N.Y., 2019 NY Slip Op 01642, First Dept 3-7-19

 

March 7, 2019
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2019-03-07 12:02:172020-01-24 05:48:42ARCHITECT’S MOTION FOR SUMMARY JUDGMENT PROPERLY DENIED, THE FACT THAT ANOTHER PARTY PLACED THE ANGLE IRON WHICH INJURED PLAINTIFF IN AN EFFORT TO FIX AN ALLEGED DEFECT IN THE DESIGN OF THE SUBJECT BOILER SYSTEM DID NOT CONSTITUTE A SUPERSEDING CAUSE OF PLAINTIFF’S INJURY AS A MATTER OF LAW (FIRST DEPT).
Architectural Malpractice, Contract Law, Negligence

CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP).

The Court of Appeals, in a full-fledged opinion by Judge DiFiore, over two partial dissenting opinions, determined the city was not a third-party beneficiary of a contract between the Dormitory Authority of the State of New York (DASNY) and defendant architects (Perkins) and the negligence cause of action (professional malpractice) by DASNY against Perkins was duplicative of the the breach of contract cause of action. Perkins had contracted with DASNY to construct a building. During excavation a neighboring building, sidewalks, sewers, etc. settled. The building gradually settled about eight inches. The majority explained when a tort action, in addition to a breach of contract action, is viable in the context of architectural malpractice:

With respect to construction contracts, we have generally required express contractual language stating that the contracting parties intended to benefit a third party by permitting that third party “to enforce [a promisee’s] contract with another” … . In the absence of express language, “[s]uch third parties are generally considered mere incidental beneficiaries” … . This rule reflects the particular nature of construction contracts and the fact that — as is the case here — there are often several contracts between various entities, with performance ultimately benefitting all of the entities involved. * * *

… [T]here are circumstances where a professional architect may be subject to a tort claim for failure to exercise due care in the performance of contractual obligations. In seeking to “disentangl[e] tort and contract claims,” we focused in Sommer both on potential catastrophic consequences of a failure to exercise due care and on the nature of the injury, the manner in which it occurred, and the resulting harm (79 NY2d at 552). We distinguished between the situation where the harm was an “abrupt, cataclysmic occurrence” not contemplated by the contracting parties and one where the plaintiff was essentially seeking enforcement of contract rights (79 NY2d at 552). Here, the … building settled during the course of several months, damaging adjacent structures. However, even if any “abrupt” or “catastrophic” consequences either could have or did result from Perkins’ alleged negligence, the fact remains that the only damages alleged appear to have been within the contemplation of the parties under the contract — and … are identical for both claims. Put another way, there was no injury alleged here that a separate negligence claim would include that is not already encompassed in DASNY’s contract claim. Dormitory Auth. of the State of N.Y. v Samson Constr. Co., 2018 NY Slip Op 01115, CtApp 2-15-18

CONTRACT LAW (CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP))/THIRD PARTY BENEFICIARY (CONSTRUCTION CONTRACT, CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP))/CONSTRUCTION CONTRACTS (THIRD PARTY BENEFICIARY, CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP))/NEGLIGENCE (ARCHITECTURAL MALPRACTICE, CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP))/ARCHITECTURAL MALPRACTICE (CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP))

February 15, 2018
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2018-02-15 15:31:112020-01-27 13:54:01CITY WAS NOT A THIRD PARTY BENEFICIARY OF A CONSTRUCTION CONTRACT BETWEEN THE DORMITORY AUTHORITY OF NYS AND DEFENDANT ARCHITECTS, MALPRACTICE ACTION AGAINST THE ARCHITECTS WAS DUPLICATIVE OF THE BREACH OF CONTRACT ACTION (CT APP).
Architectural Malpractice, Evidence, Negligence

NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT).

The Second Department, reversing Supreme Court, determined defendant architect’s motion to set aside the verdict in this professional malpractice case should have been granted. Expert testimony was required and was not presented:

… [T]he plaintiff in this case alleged that the defendants committed professional malpractice by submitting defective plans to the New York City Department of Buildings (hereinafter the DOB), and by failing to diligently pursue the approval process and timely deal with objections raised by the DOB. Such questions are not within the competence of untutored laypersons to evaluate, as “common experience and observation offer little guidance” … .

The only expert proffered by the plaintiff conceded that he “didn’t see” the defendants’ plans, and when asked, for instance, to opine on whether the defendants’ plans “would have caused a problem” regarding the roof’s ability to bear the weight of certain HVAC equipment, he demurred, answering, “No, I only work for myself.” Moreover, the expert offered no opinion regarding the defendants’ alleged delay in getting their plans approved by the DOB. Given the absence of any expert testimony that the defendants departed from accepted architectural standards of practice … , the jury lacked any rational basis for its finding that the defendants committed professional malpractice … . Michael v He Gin Lee Architect Planner, PLLC, 2017 NY Slip Op 06177, Second Dept 8-16-17

 

NEGLIGENCE (ARCHITECT MALPRACTICE, EXPERT EVIDENCE, NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/EVIDENCE (ARCHITECT MALPRACTICE, NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/PROFESSIONAL MALPRACTICE (ARCHITECTS, NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/EXPERT OPINION  (ARCHITECT MALPRACTICE, EXPERT EVIDENCE, NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/ARCHITECTS (PROFESSIONAL MALPRACTICE,  NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT))

August 16, 2017
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 CurlyHost https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png CurlyHost2017-08-16 15:09:262021-02-13 01:57:38NECESSARY EXPERT EVIDENCE WAS NOT PRESENTED BY THE PLAINTIFF IN THIS ARCHITECT MALPRACTICE CASE, THE ARCHITECT’S MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED (SECOND DEPT).
Architectural Malpractice, Contract Law, Corporation Law, Municipal Law, Negligence

DIFFERENCES BETWEEN CONTRIBUTION AND INDEMNIFICATION EXPLAINED, PERSONAL TORT LIABILITY OF CORPORATE OFFICERS NOTED.

The Second Department, in a lawsuit stemming from the flooding of plaintiffs’ land, explained the differences between contribution and indemnification and noted that corporate officers may be personally liable for torts committed in their performance of corporate duties:

The plaintiffs commenced this action against the Village of East Hills after they experienced flooding on their property from rainwater. The plaintiffs asserted causes of action sounding in tort, alleging that the flooding resulted from the development of land near their property, which was authorized by the Village. The Village commenced a third-party action seeking indemnification and contribution against A to Z Transit Contracting Corp., the project manager that constructed the plaintiffs’ home, as well as its principal, David Ferdinand, architect Carl Majowka, who prepared plans for the construction of the plaintiffs’ home, and Scott Anderson, the principal of Scott Anderson Design, Inc., which performed landscaping work for the plaintiffs’ home. * * *

“[C]ontribution arises automatically when certain factors are present and [does] not requir[e] any kind of agreement between or among the wrongdoers'” … . ” Indemnity, on the other hand, arises out of a contract which may be express or may be implied in law “to prevent a result which is regarded as unjust or unsatisfactory”‘” … . “Further, “[w]here one is held liable solely on account of the negligence of another, indemnification, not contribution, principles apply to shift the entire liability to the one who was negligent.” . . . Conversely, where a party is held liable at least partially because of its own negligence, contribution against other culpable tort-feasors is the only available remedy'”… . “Whether indemnity or contribution applies depends not upon the parties’ designation but upon a careful analysis of the theory of recovery against each tort-feasor'”       * * *

Although “[c]orporate officers may not be held personally liable on contracts of their corporations, provided they did not purport to bind themselves individually under such contracts” … , “corporate officers may be held personally liable for torts committed in the performance of their corporate duties'” … . Eisman v Village of E. Hills. 2017 NY Slip Op 02775, 2nd Dept 4-12-17

NEGLIGENCE (DIFFERENCES BETWEEN CONTRIBUTION AND INDEMNIFICATION EXPLAINED, PERSONAL TORT LIABILITY OF CORPORATE OFFICERS NOTED)/CONTRACT LAW (DIFFERENCES BETWEEN CONTRIBUTION AND INDEMNIFICATION EXPLAINED, PERSONAL TORT LIABILITY OF CORPORATE OFFICERS NOTED)/CORPORATION LAW  (DIFFERENCES BETWEEN CONTRIBUTION AND INDEMNIFICATION EXPLAINED, PERSONAL TORT LIABILITY OF CORPORATE OFFICERS NOTED)/MUNICIPAL LAW (DIFFERENCES BETWEEN CONTRIBUTION AND INDEMNIFICATION EXPLAINED, PERSONAL TORT LIABILITY OF CORPORATE OFFICERS NOTED)

April 12, 2017
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 CurlyHost https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png CurlyHost2017-04-12 15:58:152020-02-06 16:19:42DIFFERENCES BETWEEN CONTRIBUTION AND INDEMNIFICATION EXPLAINED, PERSONAL TORT LIABILITY OF CORPORATE OFFICERS NOTED.
Architectural Malpractice, Contract Law, Negligence

ARCHITECT MAY BE LIABLE FOR BOTH BREACH OF CONTRACT AND NEGLIGENCE.

The First Department, over a dissent, determined an architect, Perkins, could be sued for both breach of contract and negligence in a lawsuit stemming from the settling of a building and other structures in the vicinity of new construction. The court also concluded the plaintiff city, although not mentioned in the contract with the architect, had raised a question of fact whether the city was an intended third-party beneficiary of the contract. With respect to when a professional-party to a contract can be liable in tort, the court wrote:

Perkins, as architect, may be subject to tort liability based on a failure to exercise due care in the performance of its duties. In making this determination, the court is to look at the nature of the injury and whether the plaintiff is merely seeking the benefit of its agreement. Where the plaintiff is merely seeking the benefit of its agreement, it is limited to a contract claim … .

Where, however, “the particular project . . . is so affected with the public interest that the failure to perform competently can have catastrophic consequences,” a professional may be subject to tort liability as well … . Indeed, “[t]his is one of the most significant elements in determining whether the nature of the type of services rendered gives rise to a duty of reasonable care independent of the contract itself” (… citing Sommer v Federal Signal Corp., 79 NY2d 540, 553 [1992]). As the Court explained in Sommer, “[I]t is policy, not the parties' contract, that gives rise to a duty of care” … . The “nature of the injury, the manner in which the injury occurred and the resulting harm” are also considered … .

Here, there is a factual question whether Perkins assumed an independent legal duty as an architect to perform its work in a manner consistent with the generally accepted standard of professional care in its industry. Dormitory Auth. of the State of N.Y. v Samson Constr. Co., 2016 NY Slip Op 01546, 1st Dept 3-3-16

NEGLIGENCE (ARCHITECT MAY BE LIABLE IN TORT AND FOR BREACH OF CONTRACT)/CONTRACT LAW (ARCHITECT MAY BE LIABLE IN TORT AND FOR BREACH OF CONTRACT)/ARCHITECTS (ARCHITECT MAY BE LIABLE IN TORT AND FOR BREACH OF CONTRACT)

March 3, 2016
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 CurlyHost https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png CurlyHost2016-03-03 19:56:212020-02-06 14:53:35ARCHITECT MAY BE LIABLE FOR BOTH BREACH OF CONTRACT AND NEGLIGENCE.
Architectural Malpractice, Contract Law, Negligence

The Breach of Contract Cause of Action Which Was Based Upon Clauses Which Merely Stated the Common Law Standard of Care for Professionals Was Duplicative of the Professional Malpractice Cause of Action and Should Have Been Dismissed/Proper Measure of Damages for Negligent/Defective Building Design Is the Cost of Remediation

Plaintiff hospital alleged that the seismic retrofit of one of the hospital buildings would not operate as intended and sued the architectural firm which designed the retrofit under breach of contract and professional malpractice theories.  Plaintiff prevailed on both causes of action in a non-jury trial. The Third Department determined Supreme Court should have dismissed the breach of contract cause of action because it was duplicative of the professional malpractice cause of action. The only relevant clauses in the contract held the architectural firm to the common law standard for professionals.  Breach of those clauses, therefore, duplicated the professional malpractice cause of action. The Third Department affirmed the professional malpractice verdict and the award of damages, 1.7 million, which reflected the cost of remediation:

The contract does contain two clauses regarding defendant’s performance. They provide that defendant’s “services shall be performed as expeditiously as is consistent with professional skill and care and the orderly progress of the [w]ork,” and “shall be provided . . . in a manner consistent with the standards of care and skill exhibited in its profession for projects of this nature, type and degree of difficulty.” These provisions simply incorporate into the contract the common-law standard of care for a professional. “Making such ordinary obligations express terms of an agreement does not remove the issue [of a violation thereof] from the realm of negligence . . ., nor can it convert a malpractice action into a breach of contract action” … . Inasmuch as a breach of contract cause of action based on the violation of these particular contract provisions would be duplicative of a professional malpractice cause of action, Supreme Court should have dismissed plaintiff’s breach of contract cause of action. * * *

We reject defendant’s contention that plaintiff’s proposed amount of damages constitutes economic waste. The proper measure of damages due to the defective design of a building is the cost to remedy the defect, unless such amount is “grossly and unfairly out of proportion to the good to be attained” by fixing the building … . The defects here were not trivial, but were substantial as to the seismic function of the building, such that plaintiff was entitled to damages in the amount necessary to remediate the defects … . Mary Imogene Bassett Hosp. v Cannon Design, Inc., 2015 NY Slip Op 03016, 3rd Dept 4-9-15

 

April 9, 2015
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 CurlyHost https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png CurlyHost2015-04-09 00:00:002020-02-06 17:04:17The Breach of Contract Cause of Action Which Was Based Upon Clauses Which Merely Stated the Common Law Standard of Care for Professionals Was Duplicative of the Professional Malpractice Cause of Action and Should Have Been Dismissed/Proper Measure of Damages for Negligent/Defective Building Design Is the Cost of Remediation
Page 1 of 212

Categories

  • Abuse of Process
  • Account Stated
  • Accountant Malpractice
  • Administrative Law
  • Agency
  • Animal Law
  • Appeals
  • Arbitration
  • Architectural Malpractice
  • Associations
  • Attorneys
  • Banking Law
  • Bankruptcy
  • Battery
  • Chiropractor Malpractice
  • Civil Commitment
  • Civil Conspiracy
  • Civil Forfeiture
  • Civil Procedure
  • Civil Rights Law
  • Condominiums
  • Constitutional Law
  • Consumer Law
  • Contempt
  • Contract Law
  • Conversion
  • Cooperatives
  • Copyright
  • Corporation Law
  • Correction Law
  • Court of Claims
  • Criminal Law
  • Debtor-Creditor
  • Defamation
  • Dental Malpractice
  • Disciplinary Hearings (Inmates)
  • Education-School Law
  • Election Law
  • Eminent Domain
  • Employment Law
  • Engineering Malpractice
  • Environmental Law
  • Evidence
  • Fair Credit Reporting Act
  • Fair Housing Act
  • Fair Housing Amendments Act
  • False Arrest
  • False Claims Act
  • False Imprisonment
  • Family Law
  • Federal Employers' Liability Act (FELA)
  • Fiduciary Duty
  • Foreclosure
  • Fraud
  • Freedom of Information Law (FOIL)
  • Human Rights Law
  • Immigration Law
  • Immunity
  • Indian Law
  • Insurance Law
  • Intellectual Property
  • Intentional Infliction of Emotional Distress
  • Involuntary Medical Treatment and Feeding (Inmates)
  • Judges
  • Labor Law
  • Labor Law-Construction Law
  • Land Use
  • Landlord-Tenant
  • Legal Malpractice
  • Lien Law
  • Limited Liability Company Law
  • Longshoreman's and Harbor Worker's Compensation Act
  • Malicious Prosecution
  • Maritime Law
  • Medicaid
  • Medical Malpractice
  • Mental Hygiene Law
  • Military Law
  • Money Had and Received
  • Municipal Law
  • Navigation Law
  • Negligence
  • Negligent Infliction of Emotional Distress
  • Negligent Misrepresentation
  • Notarial Misconduct
  • Nuisance
  • Partnership Law
  • Personal Property
  • Pharmacist Malpractice
  • Physician Patient Confidentiality
  • Pistol Permits
  • Prima Facie Tort
  • Private Nuisance
  • Privilege
  • Products Liability
  • Public Authorities Law
  • Public Corporations
  • Public Health Law
  • Public Nuisance
  • Real Estate
  • Real Property Actions and Proceedings Law (RPAPL)
  • Real Property Law
  • Real Property Tax Law
  • Religion
  • Replevin
  • Retirement and Social Security Law
  • Securities
  • Sepulcher
  • Sex Offender Registration Act (SORA)
  • Social Services Law
  • Statutes
  • Tax Law
  • Tenant Harassment
  • Tortious Interference with Contract
  • Tortious Interference with Employment
  • Tortious Interference with Prospective Business Relations
  • Tortious Interference With Prospective Economic Advantage
  • Toxic Torts
  • Trade Secrets
  • Trademarks
  • Trespass
  • Trusts and Estates
  • Unemployment Insurance
  • Unfair Competition
  • Uniform Commercial Code
  • Usury
  • Utilities
  • Vehicle and Traffic Law
  • Victims of Gender-Motivated Violence Protection Law (VGM)
  • Water Law
  • Workers' Compensation
  • Zoning

Sign Up for the Mailing List to Be Notified When the Site Is Updated.

Copyright © 2023 New York Appellate Digest, LLC
Site by CurlyHost | Privacy Policy

Scroll to top