“No Damages for Delay” and “Mandatory Notice” Clauses Precluded Suit
The Third Department affirmed the dismissal of plaintiff’s breach of contract complaint, finding that the exceptions to the enforceability of a “no damages for delay” clause did not apply, and the “mandatory notice” clause precluded suit for “extra work.” Plaintiff was engaged by defendant to install heating, ventilation and air conditioning equipment:
As a general rule, “contract clauses exculpating the contractee from liability to the contractor for damages resulting from delays in performance of the contract work” are valid and enforceable … . However, even where the contract contains such a clause, there are several recognized exceptions. As relevant here, a contractor may still recover for “delays caused by the contractee’s bad faith or its willful, malicious, or grossly negligent conduct” … . A defendant seeking summary judgment dismissing a claim for delay damages “bears the initial burden of demonstrating prima facie that none of the exceptions to the ‘damages for delay’ clause are present” … . * * *
… [P]laintiff attempts to claim compensation for tasks that allegedly constituted “extra work” beyond the scope of the parties’ contract. However, a provision in the contract required plaintiff to notify defendant that it considered a task to constitute extra work within 15 working days after being ordered to undertake the task or beginning to perform it. Here, plaintiff concedes that it did not notify defendant of this claim until five months after it began performance of the disputed task. Thus, “[d]efendant established its entitlement to summary judgment by submitting proof that [plaintiff] did not comply with the condition precedent” by providing timely notice … . Tougher Indus., Inc. v Dormitory Auth. of the State of N.Y., 2015 NY Slip Op 06388, 3rd Dept 7-30-15