The Second Department, reversing Supreme Court, determined the attorney-defendants’ motion to dismiss the malpractice complaint should have been granted. The allegations of malpractice were deemed insufficient and were “utterly refuted” by the documentary evidence submitted. The court explained the analytical criteria:

“To state a cause of action to recover damages for legal malpractice, a plaintiff must allege: (1) that the attorney failed to exercise the ordinary reasonable skill and knowledge commonly possessed by a member of the legal profession; and (2) that the attorney’s breach of the duty proximately caused the plaintiff actual and ascertainable damages” … . “To establish causation, a plaintiff must show that he or she would have prevailed in the underlying action or would not have incurred any damages but for the lawyer’s negligence” … . “A claim for legal malpractice is viable, despite settlement of the underlying action, if it is alleged that settlement of the action was effectively compelled by the mistakes of counsel” … . “[A] plaintiff must plead and prove actual, ascertainable damages as a result of an attorney’s negligence” … . “Conclusory allegations of damages or injuries predicated on speculation cannot suffice for a malpractice action, and dismissal is warranted where the allegations in the complaint are merely conclusory and speculative” … . Janker v Silver, Forrester & Lesser, P.C., 2016 NY Slip Op 00481, 2nd Dept 1-27-16

ATTORNEYS (MALPRACTICE ALLEGATIONS INSUFFICIENT)/NEGLIGENCE (ALLEGATIONS OF ATTORNEY MALPRACTICE INSUFFICIENT)/LEGAL MALPRACTICE (ALLEGATIONS INSUFFICIENT)/CIVIL PROCEDURE (ALLEGATIONS OF ATTORNEY MALPRACTICE INSUFFICIENT)

In finding the town planning board’s motion for summary judgment on several causes of action brought by respondent developer should have been granted, the Second Department explained (1) the finality rule need not be mechanically applied where it is clear further administrative proceedings would be futile, and (2) the developer did not have a property interest in a site plan approval which would support a violation-of-due-process cause of action:

 

“To determine whether a matter is ripe for judicial review, it is necessary first to determine whether the issues tendered are appropriate for judicial resolution, and second to assess the hardship to the parties if judicial relief is denied'” … . “The concept of finality requires an examination of the completeness of the administrative action and a pragmatic evaluation of whether the decision-maker has arrived at a definitive position on the issue that inflicts an actual, concrete injury'” … .

In the area of land use, “[a] final decision exists when a development plan has been submitted, considered and rejected by the governmental entity with the power to implement zoning regulations” … . In this regard, “[a] property owner, for example, will be excused from obtaining a final decision if pursuing an appeal to a zoning board of appeals or seeking a variance would be futile. That is, a property owner need not pursue such applications when a zoning agency lacks discretion to grant variances or has dug in its heels and made clear that all such applications will be denied” … . Additionally, an exception to the finality requirement exists where the municipal entity uses “repetitive and unfair procedures in order to avoid a final decision” … . …

[Respondent developer] alleged that it had a cognizable property interest in the approval of the application that was injured in violation of its right to due process under both the United States and New York State Constitutions. However, as the Planning Board has significant discretion in reviewing site plan applications … , East End does not have a cognizable property interest in the approval of a particular site plan application …. .  East End Resources, LLC v Town of Southold Planning Bd., 2016 NY Slip Op 00476, 2nd Dept 1-27-16

 

ADMINISTRATIVE LAW (FINALITY RULE NOT APPLIED WHERE FURTHER PROCEEDINGS FUTILE)/ZONING (DEVELOPER DID NOT HAVE PROPERTY INTEREST IN SITE PLAN APPROVAL)/DUE PROCESS (DEVELOPER DID NOT HAVE PROPERTY INTEREST IN SITE PLAN APPROVAL)/SITE PLAN (DEVELOPER DID NOT HAVE PROPERTY INTEREST IN SITE PLAN APPROVAL)

The Second Department determined plaintiffs had standing to bring a private common-law action to enjoin zoning violations by virtue of the proximity of plaintiffs’ property to defendants’ property:

 

“To establish standing to maintain a private common-law action to enjoin zoning violations, a private plaintiff must establish that, due to the defendant’s activities, he or she will sustain special damages that are different in kind and degree from the community generally’ and that the asserted interests fall within the zone of interest to be protected’ by the statute or ordinance at issue” … . However, “an allegation of close proximity may give rise to an inference of injury enabling a nearby property owner to maintain an action without proof of actual injury” … . Here, the record demonstrates that the plaintiffs’ property was in close proximity to the defendants’ property and that the plaintiffs’ interests “were within the zone of interest to be protected by the zoning ordinances alleged to be violated” … . Since the appellant failed to demonstrate that the plaintiffs lacked standing to maintain this action, the Supreme Court properly denied that branch of his motion which was to dismiss the complaint pursuant to CPLR 3211(a)(3)… . Gershon v Cunninghaml, 2016 NY Slip Op 00332, 2nd Dept 1-20-16

 

ZONING (STANDING FOR PRIVATE COMMON-LAW ACTION TO ENJOIN ZONING VIOLATIONS)/STANDING (PRIVATE COMMON-LAW ACTION TO ENJOIN ZONING VIOLATIONS)

The Second Department reversed Supreme Court, in the interest of justice, because the jury instructions and verdict sheet did not accurately state the elements of malpractice based upon a lack of informed consent. Plaintiff’s motion to set aside the verdict should have been granted. The elements of a “lack of informed consent” cause of action were explained:

“[L]ack of informed consent is a distinct cause of action requiring proof of facts not contemplated by an action based merely on allegations of negligence” … . To establish a cause of action to recover damages for malpractice based on lack of informed consent, a plaintiff must prove “(1) that the person providing the professional treatment failed to disclose alternatives thereto and failed to inform the patient of reasonably foreseeable risks associated with the treatment, and the alternatives, that a reasonable medical practitioner would have disclosed in the same circumstances, (2) that a reasonably prudent patient in the same position would not have undergone the treatment if he or she had been fully informed, and (3) that the lack of informed consent is a proximate cause of the injury” … . “The third element is construed to mean that the actual procedure performed for which there was no informed consent must have been a proximate cause of the injury” … . ” To state it in other terms, the causal connection between a doctor’s failure to perform his [or her] duty to inform and a patient’s right to recover exists only when it can be shown objectively that a reasonably prudent person would have decided against the procedures actually performed. Once that causal connection has been established, the cause of action in negligent malpractice for failure to inform has been made out and a jury may properly proceed to consider plaintiff’s damages’ ” … . Figueroa-Burgos v Bieniewicz, 2016 NY Slip Op 00329, 2nd Dept 1-20-16

NEGLIGENCE (VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)/MEDICAL MALPRACTICE (VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)/CIVIL PROCEDURE (VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)/JURIES (JURY INSTRUCTIONS AND VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)/JURY INSTRUCTIONS (JURY INSTRUCTIONS AND VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)/VERDICT SHEET (JURY INSTRUCTIONS AND VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)/INFORMED CONSENT, LACK OF (JURY INSTRUCTIONS AND VERDICT SHEET DID NOT ACCURATELY STATE THE ELEMENTS OF A LACK-OF-INFORMED-CONSENT CAUSE OF ACTION, MOTION TO SET ASIDE THE VERDICT SHOULD HAVE BEEN GRANTED)

The Second Department, reversing Supreme Court, determined plaintiff golfer assumed the risk of slipping on a wet railroad tie which lined a path on the golf course:

 

Among the risks inherent in participating in a sport are the risks involved in the construction of the field, and any open and obvious conditions of the place where the sport is played … .

“[A]wareness of risk is not to be determined in a vacuum. It is, rather, to be assessed against the background of the skill and experience of the particular plaintiff” … . Moreover, “[i]t is not necessary to the application of assumption of risk that the injured plaintiff [had] foreseen the exact manner in which his or her injury occurred, so long as he or she is aware of the potential for injury of the mechanism from which the injury results” … . While participants are not deemed to have assumed the risks of concealed or unreasonably increased risks … , if “the risks are fully comprehended or obvious and the plaintiff has consented to them, the defendant has satisfied its only duty of care which is to make the conditions as safe as they appear to be” … . Bryant v Town of Brookhaven, 2016 NY Slip Op 00323, 2nd Dept 1-20-16

 

NEGLIGENCE (GOLFER ASSUMED RISK OF SLIPPING ON GOLF COURSE PATH)/ASSUMPTION OF RISK (GOLFER ASSUMED RISK OF SLIPPING ON GOLF COURS PATH)

The Second Department, reversing Supreme Court, determined defendants had raised a triable issue of fact about whether plaintiff had their permission to work when plaintiff fell from a scaffold. The definition of an employee under the Labor Law includes “permission to work.” Here the defendants alleged plaintiff was specifically told not to work until certain demolition work was done:

The Labor Law defines “employee” as “a mechanic, workingman or laborer working for another for hire” (Labor Law § 2[5]), and “employed” as “permitted or suffered to work” (Labor Law § 2[7]). “To come within the special class for whose benefit absolute liability is imposed upon contractors, owners, and their agents to furnish safe equipment for employees under section 240 of the Labor Law, a plaintiff must demonstrate that he was both permitted or suffered to work on a building or structure and that he was hired by someone, be it owner, contractor or their agent” … . Aslam v Neighborhood Partnership Hous. Dev. Fund Co., Inc., 2016 NY Slip Op 00316, 2nd Dept 1-20-16

LABOR LAW (DEFINITION OF EMPLOYEE INCLUDES PERMISSION TO WORK, HERE ALLEGATION EMPLOYEE WAS TOLD NOT WORK RAISED ISSUE OF FACT ON LIABILITY)/EMPLOYEE (LABOR LAW DEFINITION INCLUDES REQUIREMENT THAT EMPLOYEE HAVE PERMISSION TO WORK)

The Second Department determined Supreme Court properly found the bank did not negotiate in a mortgage foreclosure settlement conference (CPLR 3408(f)) in good faith and properly imposed certain sanctions on the bank:

 

Pursuant to CPLR 3408(f), the parties at a mandatory foreclosure settlement conference are required to negotiate in good faith to reach a mutually agreeable resolution (see CPLR 3408[f]…). ” The purpose of the good faith requirement [in CPLR 3408] is to ensure that both plaintiff and defendant are prepared to participate in a meaningful effort at the settlement conference to reach resolution'” … . To conclude that a party failed to negotiate in good faith pursuant to CPLR 3408(f), a court must determine that “the totality of the circumstances demonstrates that the party’s conduct did not constitute a meaningful effort at reaching a resolution” … .

Here, contrary to the Bank’s contention, the totality of the circumstances support the Supreme Court’s conclusion that it failed to negotiate in good faith. The homeowner’s submissions demonstrated that the Bank, among other things, engaged in dilatory conduct by “making piecemeal document requests, providing contradictory information, and repeatedly requesting documents which had already been provided” … . The Bank failed to offer any evidence in opposition to the homeowner’s motion and did not controvert the homeowner’s account of the mandatory settlement negotiations. Accordingly, under the circumstances, the Supreme Court properly concluded that the Bank violated CPLR 3408(f) by failing to negotiate in good faith … . LaSalle Bank, N.A. v Dono, 2016 NY Slip Op 00340, 2nd Dept 1-20-16

 

FORECLOSURE (BANK DID NOT NEGOTIATE IN GOOD FAITH RE: MANDATORY FORECLOSURE SETTLEMENT CONFERENCE)/CIVIL PROCEDURE (BANK DID NOT NEGOTIATE IN GOOD FAITH IN MANDATORY FORECLOSURE SETTLEMENT CONFERENCE)

The Second Department determined an agreement, called a mahr agreement, which was part of a foreign Islamic divorce decree and which called for the payment to the wife of $250,000, was properly enforced by Supreme Court under the doctrine of comity:

 

“Although not required to do so, the courts of this State generally will accord recognition to the judgments rendered in a foreign country under the doctrine of comity which is the equivalent of full faith and credit given by the courts to judgments of our sister States” … . Comity should be extended to uphold the validity of a foreign divorce decree absent a showing of fraud in its procurement or that recognition of the judgment would do violence to a strong public policy of New York … . Moreover, in extending comity to uphold the validity of a foreign divorce decree, New York courts will generally recognize all the provisions of such decrees, including any agreement which may have been incorporated therein, unless modification is required by reason of some compelling public policy … .

Here, the mahr agreement, although not acknowledged in accordance with Domestic Relations Law § 236(B)(3), was signed by the parties and two witnesses, as well as the Imam of the Islamic Cultural Center of New York. Under the circumstances presented, the Supreme Court properly recognized so much of the foreign judgment of divorce as incorporated the mahr agreement under the principles of comity, as no strong public policy of New York was violated thereby … . Badawi v Alesawy, 2016 NY Slip Op 00317, 2nd Dept 1-20-16

 

FAMILY LAW (AGREEMENT WHICH WAS PART OF A FOREIGN ISLAMIC DIVORCE DECREE PROPERLY ENFORCED UNDER DOCTRINE OF COMITY)/COMITY (AGREEMENT WHICH WAS PART OF FOREIGN ISLAMIC DIVORCE DECREE PROPERLY ENFORCED IN SUPREME COURT)

The Second Department, reversing Family Court, in a full-fledged opinion by Justice Chambers, determined petitioner had made showing of “good cause” for the extension of an order of protection, and the court ordered a five-year extension. The court took the opportunity to define “good cause” in this context:

 

… [I]n determining whether good cause has been established, courts should consider, but are not limited by, the following factors: the nature of the relationship between the parties, taking into account their former relationship, the circumstances leading up to the entry of the initial order of protection, and the state of the relationship at the time of the request for an extension; the frequency of interaction between the parties; any subsequent instances of domestic violence or violations of the existing order of protection; and whether the current circumstances are such that concern for the safety and well-being of the petitioner is reasonable … . * * *

The petitioner stated that, because they have a child in common, the parties continue to interact. They come into contact during litigation over custody and visitation issues and when they exchange the child at the drop-off location at the police station. The respondent also has a history of assaulting the petitioner, and their on-going discord continues. There is no evidence in the record to suggest that the petitioner’s more serious allegations were contrived. Moreover, it is undisputed that, since the entry of the subject order of protection, the respondent has pleaded guilty in the Criminal Court to disorderly conduct, and the Criminal Court has issued a two-year order of protection in favor of the petitioner. Therefore, it is clear from the record that the petitioner’s fear that the respondent may stalk, harass, or attack her is well-founded, and that the unavoidable interactions between the parties may subject her to a reoccurrence of violence … . Matter of Molloy v Molloy, 2016 NY Slip Op 00366, 2nd Dept 1-20-16

 

FAMILY LAW (GOOD CAUSE FOR EXTENSION OF ORDER OF PROTECTION WAS DEMONSTRATED, CRITERIA EXPLAINED)/ORDERS OF PROTECTION (FAMILY COURT, CRITERIA FOR DEMONSTRATION OF GOOD CAUSE FOR AN EXTENSION EXPLAINED)

The Second Department determined plaintiffs-lessees were entitled to bring a private action (pursuant to a provision of the town code) to rescind a lease, and were entitled to rescission and return of the paid rent. After paying $216,000 to lease defendant’s residential property for approximately 3 1/2 months, the plaintiffs learned defendant did not have a rental permit required by section 270 of the town code. The code provision was enacted to address overcrowding in properties rented for the summer. The Second Department held the code provision created a private right of action and the rental permit was a condition precedent to any lease. With respect to the private right of action, the court wrote:

 

Where, as here, a statute “does not explicitly provide for a private cause of action, recovery may be had under the statute only if a legislative intent to create such a right of action is fairly implied’ in the statutory provisions and their legislative history” … . This inquiry involves three factors: ” (1) whether the plaintiff is one of the class for whose particular benefit the statute was enacted; (2) whether recognition of a private right of action would promote the legislative purpose; and (3) whether creation of such a right would be consistent with the legislative scheme'” … . The third factor is often noted to be the “most important” … . Where, as here, the legislature clearly contemplated administrative enforcement of the statute, ” [t]he question then becomes whether, in addition to administrative enforcement, an implied private right of action would be consistent with the legislative scheme'”… .

The plaintiffs satisfied the first and second factors here. Town Code § 270 is intended to benefit the occupants of rental properties in the Town of Southampton by requiring owners to obtain a valid rental permit as a condition precedent to the collection of rent (see Town Code § 270-13). Moreover, the legislative purpose is promoted by preventing owners from profiting from the rental of properties that are overcrowded, substandard, or otherwise violate State and Town laws.

The third factor, requiring that a private cause of action under a statute be consistent with the legislative scheme, has also been satisfied. As the Supreme Court correctly observed, Town Code § 270 is directed toward protecting the health, safety, and well-being of persons renting homes in the Town of Southampton. In that regard, Town Code § 270-6 requires that prior to the issuance of a rental permit, the enforcement authority must “make an on-site inspection of the proposed rental property” to ensure that the property “complies with the New York State Uniform Fire Prevention and Building Code and the Code of the Town of Southampton” (Town Code § 270-6). Although Town Code § 270 is intended to be enforced by designated Town officials and provides for penalties and fines, “without the threat of recoupment of rent, aside from the possibility of administrative enforcement, there is no incentive for a landlord to obtain a license, which is an overriding concern of the Town” … . Ader v Guzman, 2016 NY Slip Op 00137, 2nd Dept 1-13-16

 

NEGLIGENCE (QUESTION OF FACT WHETHER HOTEL DEFENDANT VICARIOUSLY LIABLE FOR NEGLIGENCE OF SNOWMOBILE TOUR GUIDE UNDER APPARENT AGENCY THEORY)/AGENCY (QUESTION OF FACT WHETHER HOTEL DEFENDANT VICARIOUSLY LIABLE FOR NEGLIGENCE OF SNOWMOBILE TOUR GUIDE UNDER APPARENT AGENCY THEORY)