PLAINTIFFS WERE ENTITLED TO LIQUIDATED DAMAGES OF $1000 PER DAY FOR THE TIME PLAINTIFFS WERE UNABLE TO LIVE IN THEIR TOWNHOUSE BECAUSE OF THE DEFENDANTS’ RENOVATIONS NEXT DOOR (FIRST DEPT).

The First Department, in a decision addressing many issues not summarized here, determined the plaintiffs were entitled to liquidated damages of $1000 per day for the time plaintiffs were unable to live in their townhouse because of the renovation work undertaken by the defendants next door:

On May 2, 2013, after intensive negotiations guided by legal counsel, Mr. Seymour [plaintiff] and the Hovnanians [defendants] executed a license agreement. The purpose of the license agreement was to grant the Hovnanians 18 months of access to the Seymours’ property while simultaneously protecting the Seymours’ property from further harm during construction. The license agreement contained a liquidated damages clause providing that if the “Project Owner failed to obtain a temporary certificate of occupancy (TCO) within Eighteen (18) months from the date of this Agreement, he shall pay liquidated damages to the Adjacent Owner of $1,000 per day for every day thereafter until the TCO is issued.” The Hovnanians never obtained a temporary certificate of occupancy but, 318 days after the expiration of the 18-month license term, they obtained a certificate of occupancy. …

The court correctly awarded plaintiffs $318,000 in liquidated damages, plus interest, comprised of $1,000 per day for the period of November 2, 2014 to September 15, 2015. “Liquidated damages constitute the compensation which, the parties have agreed, should be paid in order to satisfy any loss or injury flowing from a breach of their contract” … . These provisions “have value in those situations where it would be difficult, if not actually impossible, to calculate the amount of actual damage” … . Liquidated damages will be sustained if, at the time of the contract, “the amount liquidated bears a reasonable proportion to the probable loss and the amount of actual loss is incapable or difficult of precise estimation” … . Seymour v Hovnanian, 2022 NY Slip Op 07172, First Dept 12-15-22

Practice Point: Here the license agreement properly required liquidated damages of $1000 per day for the time plaintiffs were not able to live in their townhouse because of defendants’ renovations next door.

 

December 15, 2022
Tags: First Department
Share this entry
  • Share on WhatsApp
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 Bruce Freeman https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png Bruce Freeman2022-12-15 16:00:032022-12-16 16:23:59PLAINTIFFS WERE ENTITLED TO LIQUIDATED DAMAGES OF $1000 PER DAY FOR THE TIME PLAINTIFFS WERE UNABLE TO LIVE IN THEIR TOWNHOUSE BECAUSE OF THE DEFENDANTS’ RENOVATIONS NEXT DOOR (FIRST DEPT).
You might also like
TRIAL COURT VIOLATED THE LAW OF THE CASE DOCTRINE, PRIOR RULING BY THE COMMERCIAL DIVISION BECAME THE LAW OF THE CASE (SECOND DEPT).
Verdict for Negligent Design Upheld—1987 Car Did Not Have a Starter Interlock Device that Would Prevent Car from Starting When In Gear
INJURY CAUSED BY CEMENT BOARDS FALLING FROM AN A-FRAME CART COVERED UNDER LABOR LAW 240 (1) (FIRST DEPT).
THE WARRANT ENTITLING PLAINTIFF TO MORE THAN 1100 SHARES OF DEFENDANT CORPORATION’S STOCK WAS APPENDED TO PLAINTIFF’S EMPLOYMENT CONTRACT WITH DEFENDANT; THE TWO CONTRACTS DID NOT MERGE AND ANY ALLEGED BREACH OF THE EMPLOYMENT CONTRACT BY PLAINTIFF DID NOT PRECLUDE THE ENFORCEMENT OF THE WARRANT (FIRST DEPT).
PLAINTIFFS’ EXPERTS PRESENTED SUFFICIENT PROOF TO WARRANT A FRYE HEARING ON WHETHER A TUMOR MAY HAVE BEEN DETECTABLE BEFORE BIRTH.
FAILURE TO INFORM JURY OF EFFECT OF ACQUITTAL ON THE TOP COUNT BASED ON THE JUSTIFCATION DEFENSE REQUIRED REVERSAL IN THE INTEREST OF JUSTICE.
WIFE ENTITLED TO A PERCENTAGE OF HUSBAND’S ENHANCED EARNING CAPACITY BY ENABLING HUSBAND’S LONG WORKING HOURS AND HIS STUDY FOR MEDICAL BOARD EXAMS.
DEFENDANT, A PODIATRIST, USING ALTERNATIVE MEDICINE (OZONE THERAPY), TREATED PLAINTIFF FOR LYME DISEASE; DEFENDANT DID NOT SUBMIT PROOF OF THE APPLICABLE STANDARD OF CARE; DEFENDANT’S MOTION FOR SUMMARY JUDGMENT IN THIS MEDICAL MALPRACTICE ACTION SHOULD NOT HAVE BEEN GRANTED (FIRST DEPT).

Categories

  • Abuse of Process
  • Account Stated
  • Accountant Malpractice
  • Administrative Law
  • Agency
  • Animal Law
  • Appeals
  • Arbitration
  • Architectural Malpractice
  • Arts and Cultural Affairs Law
  • Associations
  • Attorneys
  • Banking Law
  • Bankruptcy
  • Battery
  • Chiropractor Malpractice
  • Civil Commitment
  • Civil Conspiracy
  • Civil Forfeiture
  • Civil Procedure
  • Civil Rights Law
  • Condominium Corporations
  • Condominiums
  • Constitutional Law
  • Consumer Law
  • Contempt
  • Contract Law
  • Conversion
  • Cooperatives
  • Copyright
  • Corporation Law
  • Correction Law
  • County Law
  • Court of Claims
  • Criminal Law
  • Debtor-Creditor
  • Defamation
  • Dental Malpractice
  • Disciplinary Hearings (Inmates)
  • Education-School Law
  • Election Law
  • Eminent Domain
  • Employment Law
  • Engineering Malpractice
  • Environmental Law
  • Equitable Recoupment
  • Evidence
  • Fair Credit Reporting Act
  • Fair Housing Act
  • Fair Housing Amendments Act
  • False Arrest
  • False Claims Act
  • False Imprisonment
  • Family Law
  • Federal Employers' Liability Act (FELA)
  • Fiduciary Duty
  • Forcible Touching
  • Foreclosure
  • Fraud
  • Freedom of Information Law (FOIL)
  • Human Rights Law
  • Immigration Law
  • Immunity
  • Indian Law
  • Insurance Law
  • Intellectual Property
  • Intentional Infliction of Emotional Distress
  • Involuntary Medical Treatment and Feeding (Inmates)
  • Judges
  • Judiciary Law
  • Labor Law
  • Labor Law-Construction Law
  • Land Use
  • Landlord-Tenant
  • Legal Malpractice
  • Lien Law
  • Limited Liability Company Law
  • Longshoreman's and Harbor Worker's Compensation Act
  • Malicious Prosecution
  • Maritime Law
  • Medicaid
  • Medical Malpractice
  • Mental Hygiene Law
  • Military Law
  • Money Had and Received
  • Municipal Law
  • Navigation Law
  • Negligence
  • Negligent Infliction of Emotional Distress
  • Negligent Misrepresentation
  • Notarial Misconduct
  • Nuisance
  • Partnership Law
  • Personal Property
  • Pharmacist Malpractice
  • Physician Patient Confidentiality
  • Pistol Permits
  • Prima Facie Tort
  • Private Nuisance
  • Privilege
  • Products Liability
  • Professional Malpractice
  • Public Authorities Law
  • Public Corporations
  • Public Health Law
  • Public Nuisance
  • Real Estate
  • Real Property Actions and Proceedings Law (RPAPL)
  • Real Property Law
  • Real Property Tax Law
  • Religion
  • Replevin
  • Retirement and Social Security Law
  • Securities
  • Sepulcher
  • Sex Offender Registration Act (SORA)
  • Social Services Law
  • Statutes
  • Tax Law
  • Tenant Harassment
  • Tortious Interference with Contract
  • Tortious Interference with Employment
  • Tortious Interference with Prospective Business Relations
  • Tortious Interference With Prospective Economic Advantage
  • Town Law
  • Toxic Torts
  • Trade Secrets
  • Trademarks
  • Trespass
  • Trespass to Chattels
  • Trusts and Estates
  • Uncategorized
  • Unemployment Insurance
  • Unfair Competition
  • Uniform Commercial Code
  • Usury
  • Utilities
  • Vehicle and Traffic Law
  • Victims of Gender-Motivated Violence Protection Law (VGM)
  • Village Law
  • Water Law
  • Workers' Compensation
  • Zoning

Sign Up for the Mailing List to Be Notified When the Site Is Updated.

  • This field is for validation purposes and should be left unchanged.

Copyright © 2026 New York Appellate Digest, Inc.
Site by CurlyHost | Privacy Policy

YESHIVA UNIVERSITY NO LONGER HAS THE REQUISITE CONNECTION TO RELIGION AND THEREFORE... DEFENDANT’S STATEMENT PLAINTIFFS WERE FACING SUSPENSION OF THEIR LICENSE...
Scroll to top