PETITIONERS DID NOT TAKE STEPS TO PRESERVE THE STATUS QUO AS THEY SOUGHT TO VACATE A CONSTRUCTION CONTRACT; THE CONSTRUCTION PROGRESSED TO THE POINT WHERE THE COURT MUST DISMISS THE APPEAL AS MOOT (THIRD DEPT).
The Third Department determined the petitioners’ appeal of the denial of a declaratory judgment seeking to vacate the award of a construction contract by the Office of State Comptroller (OSC) must be dismissed as moot. The petitioners did not seek to maintain the status quo by injunction and the work had progressed too far:
… [T]he doctrine of mootness is invoked where a change in circumstances prevents a court from rendering a decision that would effectively determine an actual controversy” … . Where a change in circumstances involves the substantial completion of construction, “courts must consider several factors, including whether the challengers sought preliminary injunctive relief or otherwise attempted to preserve the status quo to prevent construction from commencing or continuing during the pendency of the litigation”… . Although injunctive relief is theoretically available, as a project can be dismantled, courts consider how far the work has progressed toward completion in determining mootness … . Matter of Bothar Constr., LLC v Dominguez, 2022 NY Slip Op 00346, Third Dept 1-20-22