THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT).
The Second Department determined plaintiff's motion to dismiss the third-party complaint was properly granted because the third-party action was commenced four years after the suit began and would unduly delay the main action. The Second Department also determined that Supreme Court properly ordered that defendants disclose information about post-accident repairs in this stairway slip and fall case. Defendants had not disclosed the identity of the party which exercised control over the stairway:
“CPLR 1010 provides a safety valve for cases in which the third-party claim will unduly delay the determination of the main action or prejudice the substantial rights of any party'”… . Where the record indicates that a third-party plaintiff knowingly and deliberately delayed in commencing the third-party action, the Supreme Court acts within its discretion to dismiss the third-party complaint… . Contrary to the defendants' contentions, the court correctly granted the plaintiff's motion to dismiss the third-party complaint because the defendants deliberately and intentionally delayed commencing the third-party action for more than four years.
“CPLR 3101(a) requires full disclosure of all evidence material and necessary in the prosecution or defense of an action” … . ” Evidence of subsequent repairs and remedial measures is not discoverable or admissible in a negligence case unless there is an issue of maintenance or control'” … . Contrary to the defendants' contentions, an issue exists as to the identity of the entity responsible for the structural maintenance and control of the stairway. Accordingly, the Supreme Court correctly directed the defendants to produce discovery concerning the post-accident repairs. Soto v CBS Corp., 2018 NY Slip Op 00185, Second Dept 1-10-18
NEGLIGENCE (SLIP AND FALL, POST-ACCIDENT REPAIRS, THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))/EVIDENCE (SLIP AND FALL, POST-ACCIDENT REPAIRS, THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))/POST-ACCIDENT REPAIRS (SLIP AND FALL, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))/CIVIL PROCEDURE (SLIP AND FALL, POST-ACCIDENT REPAIRS, THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))/CPLR 1010 (SLIP AND FALL, POST-ACCIDENT REPAIRS, THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))/CPLR 3101 (SLIP AND FALL, POST-ACCIDENT REPAIRS, THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))/REPAIRS, POST-ACCIDENT (SLIP AND FALL, POST-ACCIDENT REPAIRS, THIRD PARTY COMPLAINT PROPERLY DISMISSED AS CAUSING UNDUE DELAY OF THE MAIN ACTION, DISCOVERY OF POST-ACCIDENT REPAIRS OF STAIRWAY PROPERLY ORDERED IN THIS SLIP AND FALL CASE (SECOND DEPT))