New York Appellate Digest
  • Home
  • About
  • Just Released
  • Update Service
  • Streamlined Research
  • CLE Courses
  • Contact
  • Menu Menu
You are here: Home1 / Civil Procedure2 / PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED...
Civil Procedure, Contract Law, Evidence, Lien Law

PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY; CRITERIA FOR AMENDMENT OF A COMPLAINT TO CONFORM TO TRIAL PROOF DESCRIBED.

In an action to foreclose a mechanic’s lien, the Second Department determined Supreme Court properly allowed amendment of the pleadings to conform with the proof, which was consistent with an action for quantum meruit. Plaintiff contractor was unable to show the value of the work performed, so plaintiff’s Lien Law and quantum meruit actions failed. Similarly, the defendants failed to prove they ended up paying more than the original agreed price for the work. So defendants’ counterclaims for breach of contract and damages failed. With respect to the amendment of the complaint to conform to the proof, and the flaws in plaintiff’s proof of the value of plaintiff’s work, the court wrote:

Pursuant to Lien Law § 3, a contractor who performs labor or furnishes materials for the improvement of real property with the consent, or at the request of, the owner “shall have a lien for the principal and interest, of the value, or the agreed price, of such labor . . . or materials upon the real property improved or to be improved and upon such improvement.” “A lienor may seek amounts due from both written contracts and from change orders for extras, depending on whether the owner gave his consent for the extra work” … . The lienor’s right to recover is limited by the contract price or the reasonable value of the labor and materials provided … . The lienor has the burden of establishing the amount of the outstanding debt by proffering proof either of the price of the contract or the value of labor and materials supplied … .

… [P]laintiff failed to offer bills, invoices, receipts, time sheets, checks, or any other evidence which would establish the cost of materials, work done by subcontractors, or the number of hours he worked on the job and proffered no explanation for his failure to present this evidence. He likewise failed to provide any detailed description of the work performed, the cost of any portion of the work, or the hourly rate at which he valued his labor. Indeed, at trial, the plaintiff admitted that the sum asserted in his lien was only an estimate. … .

Pursuant to CPLR 3025(c), a trial court may permit the amendment of pleadings before or after judgment to conform them to the evidence “upon such terms as may be just” … .Here, although the complaint sought recovery in the form of foreclosure on his mechanic’s lien, at trial, the plaintiff sought to conform the pleadings to the proof and assert a cause of action for recovery in quantum meruit. The Supreme Court granted that motion, and therefore, contrary to the defendants’ contention, that theory of recovery was properly before the court. * * *

Here, although the plaintiff presented evidence satisfying … three elements [of quntum meruit], this cause of action must fail for the same reason that the cause of action to foreclose his mechanic’s lien must fail; namely, his failure to present any evidence of the value of the materials supplied or services rendered. DiSario v Rynston, 2016 NY Slip Op 02611, 2nd Dept 4-6-16

CONTRACT LAW (PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY)/QUANTUM MERUIT (PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY)/MECHANIC’S LIEN (PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY)/LIEN LAW (PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY)/EVIDENCE (PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY)/CIVIL PROCEDURE (CRITERIA FOR AMENDMENT OF A COMPLAINT TO CONFORM TO TRIAL PROOF DESCRIBED)/COMPLAINT, AMENDMENT OF (CRITERIA FOR AMENDMENT OF A COMPLAINT TO CONFORM TO TRIAL PROOF DESCRIBED)

April 6, 2016
Tags: Second Department
Share this entry
  • Share on WhatsApp
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 CurlyHost https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png CurlyHost2016-04-06 14:24:162020-02-06 12:52:20PLAINTIFF-CONTRACTOR’S FAILURE TO PROVE THE VALUE OF THE WORK PRECLUDED RECOVERY UNDER THE LIEN LAW AND UNDER A QUANTUM MERUIT THEORY; CRITERIA FOR AMENDMENT OF A COMPLAINT TO CONFORM TO TRIAL PROOF DESCRIBED.
You might also like
THE MANNER IN WHICH THE FIREFIGHTER’S GENERAL MUNICIPAL LAW 207-A INJURY CLAIM SHOULD BE PROCESSED IS ARBITRABLE BECAUSE THE ISSUE IS ADDRESSED IN THE COLLECTIVE BARGANING AGREEMENT (CBA); THE PETITION TO STAY ARBITRATION SHOULD NOT HAVE BEEN GRANTED (SECOND DEPT).
CALCULATION OF ENHANCED EARNING CAPACITY STEMMING FROM A DEGREE EARNED DURING MARRIAGE IN THE CONTEXT OF ALLOCATING MARITAL PROPERTY IN A DIVORCE PROCEEDING EXPLAINED (SECOND DEPT).
THE CUSTODY ARRANGEMENTS SET FORTH IN A SETTLEMENT AGREEMENT SHOULD NOT HAVE BEEN MODIFIED IN THE ABSENCE OF A HEARING AND FAMILY COURT SHOULD NOT HAVE RELIED ON INADMISSIBLE EVIDENCE UNTESTED BY THE PARTIES (SECOND DEPT).
PLAINTIFF’S MOTION FOR JUDGMENT AS A MATTER OF LAW SHOULD HAVE BEEN GRANTED, DESK LEFT UNATTENDED ON A DOLLY BY DEFENDANT MOVER FELL OVER ONTO PLAINTIFF (SECOND DEPT).
PLAINTIFF CONTRACTOR DID NOT ALLEGE IT WAS LICENSED TO DO HOME IMPROVEMENT WORK IN ITS COMPLAINT ALLEGING BREACH OF CONTRACT AND SEEKING TO FORECLOSE ON A MECHANIC’S LIEN, THE COMPLAINT SHOULD HAVE BEEN DISMISSED (SECOND DEPT). ​
THE BANKS’ COMPLIANCE WITH THE NOTICE REQUIREMENTS OF RPAPL 1304 WAS NOT DEMONSTRATED; THE BANK’S MOTION FOR SUMMARY JUDGMENT IN THIS FORECLOSURE ACTION SHOULD NOT HAVE BEEN GRANTED (SECOND DEPT).
FAILURE TO COMPLY WITH DISCOVERY DEMANDS WARRANTED STRIKING THE ANSWER.
PURSUANT TO AN EXCEPTION IN 22 NYCRR 202.5-b, USING THE NYSCEF ELECTRONIC FILING SYSTEM DID NOT CONSTITUTE PROPER SERVICE OF A NOTICE OF ENTRY ON DEFENDANTS, THE TIME FOR DEFENDANTS TO ANSWER THEREFORE NEVER STARTED TO RUN AND DEFENDANTS WERE NOT IN DEFAULT (SECOND DEPT).

Categories

  • Abuse of Process
  • Account Stated
  • Accountant Malpractice
  • Administrative Law
  • Agency
  • Animal Law
  • Appeals
  • Arbitration
  • Architectural Malpractice
  • Associations
  • Attorneys
  • Banking Law
  • Bankruptcy
  • Battery
  • Chiropractor Malpractice
  • Civil Commitment
  • Civil Conspiracy
  • Civil Forfeiture
  • Civil Procedure
  • Civil Rights Law
  • Condominiums
  • Constitutional Law
  • Consumer Law
  • Contempt
  • Contract Law
  • Conversion
  • Cooperatives
  • Copyright
  • Corporation Law
  • Correction Law
  • Court of Claims
  • Criminal Law
  • Debtor-Creditor
  • Defamation
  • Dental Malpractice
  • Disciplinary Hearings (Inmates)
  • Education-School Law
  • Election Law
  • Eminent Domain
  • Employment Law
  • Engineering Malpractice
  • Environmental Law
  • Evidence
  • Fair Credit Reporting Act
  • Fair Housing Act
  • Fair Housing Amendments Act
  • False Arrest
  • False Claims Act
  • False Imprisonment
  • Family Law
  • Federal Employers' Liability Act (FELA)
  • Fiduciary Duty
  • Foreclosure
  • Fraud
  • Freedom of Information Law (FOIL)
  • Human Rights Law
  • Immigration Law
  • Immunity
  • Indian Law
  • Insurance Law
  • Intellectual Property
  • Intentional Infliction of Emotional Distress
  • Involuntary Medical Treatment and Feeding (Inmates)
  • Judges
  • Labor Law
  • Labor Law-Construction Law
  • Land Use
  • Landlord-Tenant
  • Legal Malpractice
  • Lien Law
  • Limited Liability Company Law
  • Longshoreman's and Harbor Worker's Compensation Act
  • Malicious Prosecution
  • Maritime Law
  • Medicaid
  • Medical Malpractice
  • Mental Hygiene Law
  • Military Law
  • Money Had and Received
  • Municipal Law
  • Navigation Law
  • Negligence
  • Negligent Infliction of Emotional Distress
  • Negligent Misrepresentation
  • Notarial Misconduct
  • Nuisance
  • Partnership Law
  • Personal Property
  • Pharmacist Malpractice
  • Physician Patient Confidentiality
  • Pistol Permits
  • Prima Facie Tort
  • Private Nuisance
  • Privilege
  • Products Liability
  • Public Authorities Law
  • Public Corporations
  • Public Health Law
  • Public Nuisance
  • Real Estate
  • Real Property Actions and Proceedings Law (RPAPL)
  • Real Property Law
  • Real Property Tax Law
  • Religion
  • Replevin
  • Retirement and Social Security Law
  • Securities
  • Sepulcher
  • Sex Offender Registration Act (SORA)
  • Social Services Law
  • Statutes
  • Tax Law
  • Tenant Harassment
  • Tortious Interference with Contract
  • Tortious Interference with Employment
  • Tortious Interference with Prospective Business Relations
  • Tortious Interference With Prospective Economic Advantage
  • Toxic Torts
  • Trade Secrets
  • Trademarks
  • Trespass
  • Trusts and Estates
  • Unemployment Insurance
  • Unfair Competition
  • Uniform Commercial Code
  • Usury
  • Utilities
  • Vehicle and Traffic Law
  • Victims of Gender-Motivated Violence Protection Law (VGM)
  • Water Law
  • Workers' Compensation
  • Zoning

Sign Up for the Mailing List to Be Notified When the Site Is Updated.

Copyright © 2023 New York Appellate Digest, LLC
Site by CurlyHost | Privacy Policy

UNLICENSED CONTRACTOR CAN NOT RECOVER UNDER HOME IMPROVEMENT CONTRACT OR IN... CORPORATE VEIL PIERCED TO ENFORCE JUDGMENTS.
Scroll to top