CLAIMANTS’ MOTION FOR LEAVE TO FILE AND SERVE A LATE NOTICE OF CLAIM IN THIS CONSTRUCTION-ACCIDENT CASE SHOULD HAVE BEEN GRANTED (SECOND DEPT).
The Second Department, reversing the Court of Claims, determined claimants’ should have been allowed to file a late notice of claim in this construction accident case. The delay in filing was minimal, claimants made a sufficient showing the defendants were not prejudiced by the delay and defendants did not demonstrate prejudice:
The claimants showed that any delay in ascertaining actual notice of all of the essential facts underlying the claims was minimal … , and that the defendants were provided with an adequate opportunity to investigate the circumstances underlying the claims in light of, among other things, the information contained in an accident report and a medical release, which were both prepared by the defendants’ general contractor on the date of the accident…. . …
… [T]he defendants failed to come forward with “a particularized evidentiary showing that [they] will be substantially prejudiced” if the late claims are permitted … . Schnier v New York State Thruway Auth., 2022 NY Slip Op 03267, Second Dept 5-18-22
Practice Point: The claimants adequately demonstrated defendants in this construction-accident case were not prejudiced by the minimal delay in filing the notice of claim and defendants were unable to demonstrate any prejudice as they had time to investigate the incident after timely receiving the accident report. Claimants’ motion for leave to file and serve a late notice of claim should have been granted.