THE STATE PROPERLY APPROVED THE CONSTRUCTION OF ELECTICITY-GENERATING WIND TURBINES IN WESTERN NEW YORK (FOURTH DEPT).
The Fourth Department, affirming the approval of the construction of wind turbines for generating electricity by the NYS Board on Electric Generation Siting and the Environment (Board), determined: (1) the correct local wind-turbine law for the Town of Freedom was considered by the Board; (2) the Board correctly refused to consider a local wind-turbine law for the Town of Farmersville enacted after the evidentiary phase of the project was complete; (3) the Board properly considered the climate-change effects of the project and the effects on wild life and the land; and (4) the coalition contesting the Board ruling did not have standing to represent the First Amendment rights of the Amish community:
… [T]he Board must determine … whether a proposed electric generating facility “is a beneficial addition to or substitution for the electric generation capacity of the state” and whether “the adverse environmental effects of the construction and operation of the facility will be minimized or avoided to the maximum extent practicable” (Public Service Law § 168 [3] [a], [c]), and the Board must consider … “the impact on community character” and any additional “social, economic, visual or other aesthetic, environmental and other conditions” deemed pertinent by the Board … . “[T]he Board was created to provide for an expeditious review process and ‘to balance, in a single proceeding, the people’s need for electricity and their environmental concerns’ ” … . Furthermore, it is settled that “[t]his [C]ourt’s scope of review is limited to whether the decision and opinion of the [B]oard, inter alia, are . . . supported by substantial evidence in the record and matters of judicial notice properly considered and applied in the opinion . . . , are made in accordance with proper procedure . . . and are not arbitrary, capricious or an abuse of discretion” … . “The task of weighing conflicting evidence . . . is properly left to the . . . Board” … . Matter of Coalition of Concerned Citizens v New York State Bd. On Elec. Generation Siting & The Envt. & Alle-Catt Wind Energy, LLC, 2021 NY Slip Op 06221, Fourth Dept 11-12-21