New York Appellate Digest
  • Home
  • About
  • Just Released
  • Update Service
  • Streamlined Research
  • CLE Courses
  • Contact
  • Menu Menu
You are here: Home1 / Environmental Law2 / PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED...
Environmental Law, Land Use, Municipal Law, Zoning

PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT).

The Second Department, reversing Supreme Court, determined that the town planning board’s approval of the development of land should be annulled. The land included wetlands which required an investigation and approval by the Army Corps of Engineers (ACOE) and those requirements had not been met. The petitioners’ request for a Supplemental Environmental Impact Statement (SEIS) should have been granted:

​

“A lead agency’s determination whether to require a SEIS . . . is discretionary” … . “The lead agency may require a supplemental EIS, limited to the specific significant adverse environmental impacts not addressed or inadequately addressed in the EIS that arise from: (a) changes proposed for the project; (b) newly discovered information; or (c) a change in circumstances related to the project” … . “The decision to prepare a SEIS as a result of newly discovered information must be based upon . . . (a) the importance and relevance of the information; and (b) the present state of the information in the EIS'” … . The limitations that apply to a court’s review of an agency’s SEQRA determination, that is, only to ascertain whether the agency took a hard look at the relevant areas of environmental concern and made a reasoned elaboration of the basis for its determination, also apply to the agency’s determination regarding whether a SEIS is needed, and the court may no more substitute its judgment on this point than it may on other aspects of agency decision-making … .

Here, the petitioners contend that a SEIS is needed because Scenic never obtained a jurisdictional determination from the United States Army Corps of Engineers (hereinafter ACOE) validating  [the developer’s] delineation of wetlands on the subject property. They argue that, prior to issuing the determinations challenged on appeal, the Planning Board was presented with critical new evidence demonstrating that no jurisdictional determination had been issued by the ACOE for the subject property. The petitioners are correct. Matter of Shapiro v Planning Bd. of the Town of Ramapo, 2017 NY Slip Op 07734, Second Dept 11-8-17

 

ENVIRONMENTAL LAW (PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/ZONING (PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/MUNICIPAL LAW (PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/STATE ENVIRONMENTAL QUALITY REVIEW ACT (SEQRA)  (PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/ENVIRONMENTAL IMPACT STATEMENT (PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/WETLANDS (ENVIRONMENTAL LAW, PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))/ARMY CORPS OF ENGINEERS (ENVIRONMENTAL LAW, WETLANDS, PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT))

November 8, 2017
Tags: Second Department
Share this entry
  • Share on WhatsApp
https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png 0 0 CurlyHost https://www.newyorkappellatedigest.com/wp-content/uploads/2018/03/NYAppelateLogo-White-1.png CurlyHost2017-11-08 16:16:522020-02-06 01:19:52PLANNING BOARD’S APPROVAL OF DEVELOPMENT INCLUDING WETLANDS NEEDED APPROVAL BY THE ARMY CORPS OF ENGINEERS, REQUEST FOR A SUPPLEMENTAL ENVIRONMENTAL IMPACT STATEMENT SHOULD HAVE BEEN GRANTED (SECOND DEPT).
You might also like
911 CALL AND PRIOR CONSISTENT STATEMENT PROPERLY ADMITTED AS EXCITED UTTERANCES.
TRANSMISSION REPAIR COMPANY OWED A DUTY TO PLAINTIFF’S DECEDENT AS A THIRD PARTY BENEFICIARY OF A TRUCK REPAIR CONTRACT WITH PLAINTIFF’S DECEDENT’S EMPLOYER, IF THE TRUCK HAD BEEN EQUIPPED WITH A FUNCTIONING NEUTRAL INTERLOCK SYSTEM IT WOULD NOT HAVE LURCHED BACK, KILLING PLAINTIFF’S DECEDENT (SECOND DEPT).
DISCLOSURE OF TOWN EMAIL LIST PROPERLY ORDERED.
IN THIS CHILD VICTIMS ACT CASE ALLEGING SEXUAL ABUSE BY A TEACHER DURING THE SCHOOL DAY OVER THE COURSE OF A YEAR, PLAINTIFF RAISED QUESTIONS OF FACT UNDER BOTH RESPONDEAT SUPERIOR AND NEGLIGENT SUPERVISION CAUSES OF ACTION (SECOND DEPT).
SUPREME COURT PROPERLY DENIED PETITIONER’S MOTION TO DISCONTINUE THE PROPERTY TAX CERTIORARI PROCEEDING WITH RESPECT TO ONE OF THE TAX PARCELS BECAUSE THE TOWN’S DEFENSE COULD BE PREJUDICED, HOWEVER SUPREME COURT SHOULD NOT HAVE ORDERED THE MERGER OF TWO TAX PARCELS BECAUSE NEITHER PARTY REQUESTED THAT RELIEF (SECOND DEPT).
DEFENDANT DRIVER WAVED TO PLAINTIFF’S DECEDENT, A PEDESTRIAN, INDICATING SHE WAS ALLOWING PLAINTIFF’S DECEDENT TO CROSS THE STREET; ONE SECOND LATER PLAINTIFF’S DECEDENT WAS STRUCK BY ANOTHER CAR; THE ACCIDENT WAS THE RESULT OF A SUPERSEDING, INTERVENING ACT AND DEFENDANT WAS NOT LIABLE AS A MATTER OF LAW (SECOND DEPT).
THE ELECTRICAL-CONTRACTOR CORP WAS NOT LICENSED TO DO ELECTRICAL WORK IN NYC; THE FACT THAT THE CORPORATION’S VICE PRESIDENT WAS LICENSED AND THE VICE PRESIDENT’S COMPANY, WHICH DID THE ELECTRICAL WORK AS A SUBCONTRACTOR, WAS LICENSED DOESN’T MATTER; THE CORPORATION CAN NOT SUE FOR BREACH OF CONTRACT (SECOND DEPT). ​
Plaintiff’s Motion to Appoint a Temporary Administrator after Defendant’s Death Properly Denied—Relevant Law Explained

Categories

  • Abuse of Process
  • Account Stated
  • Accountant Malpractice
  • Administrative Law
  • Agency
  • Animal Law
  • Appeals
  • Arbitration
  • Architectural Malpractice
  • Associations
  • Attorneys
  • Banking Law
  • Bankruptcy
  • Battery
  • Chiropractor Malpractice
  • Civil Commitment
  • Civil Conspiracy
  • Civil Forfeiture
  • Civil Procedure
  • Civil Rights Law
  • Condominium Corporations
  • Condominiums
  • Constitutional Law
  • Consumer Law
  • Contempt
  • Contract Law
  • Conversion
  • Cooperatives
  • Copyright
  • Corporation Law
  • Correction Law
  • County Law
  • Court of Claims
  • Criminal Law
  • Debtor-Creditor
  • Defamation
  • Dental Malpractice
  • Disciplinary Hearings (Inmates)
  • Education-School Law
  • Election Law
  • Eminent Domain
  • Employment Law
  • Engineering Malpractice
  • Environmental Law
  • Equitable Recoupment
  • Evidence
  • Fair Credit Reporting Act
  • Fair Housing Act
  • Fair Housing Amendments Act
  • False Arrest
  • False Claims Act
  • False Imprisonment
  • Family Law
  • Federal Employers' Liability Act (FELA)
  • Fiduciary Duty
  • Foreclosure
  • Fraud
  • Freedom of Information Law (FOIL)
  • Human Rights Law
  • Immigration Law
  • Immunity
  • Indian Law
  • Insurance Law
  • Intellectual Property
  • Intentional Infliction of Emotional Distress
  • Involuntary Medical Treatment and Feeding (Inmates)
  • Judges
  • Labor Law
  • Labor Law-Construction Law
  • Land Use
  • Landlord-Tenant
  • Legal Malpractice
  • Lien Law
  • Limited Liability Company Law
  • Longshoreman's and Harbor Worker's Compensation Act
  • Malicious Prosecution
  • Maritime Law
  • Medicaid
  • Medical Malpractice
  • Mental Hygiene Law
  • Military Law
  • Money Had and Received
  • Municipal Law
  • Navigation Law
  • Negligence
  • Negligent Infliction of Emotional Distress
  • Negligent Misrepresentation
  • Notarial Misconduct
  • Nuisance
  • Partnership Law
  • Personal Property
  • Pharmacist Malpractice
  • Physician Patient Confidentiality
  • Pistol Permits
  • Prima Facie Tort
  • Private Nuisance
  • Privilege
  • Products Liability
  • Professional Malpractice
  • Public Authorities Law
  • Public Corporations
  • Public Health Law
  • Public Nuisance
  • Real Estate
  • Real Property Actions and Proceedings Law (RPAPL)
  • Real Property Law
  • Real Property Tax Law
  • Religion
  • Replevin
  • Retirement and Social Security Law
  • Securities
  • Sepulcher
  • Sex Offender Registration Act (SORA)
  • Social Services Law
  • Statutes
  • Tax Law
  • Tenant Harassment
  • Tortious Interference with Contract
  • Tortious Interference with Employment
  • Tortious Interference with Prospective Business Relations
  • Tortious Interference With Prospective Economic Advantage
  • Town Law
  • Toxic Torts
  • Trade Secrets
  • Trademarks
  • Trespass
  • Trusts and Estates
  • Uncategorized
  • Unemployment Insurance
  • Unfair Competition
  • Uniform Commercial Code
  • Usury
  • Utilities
  • Vehicle and Traffic Law
  • Victims of Gender-Motivated Violence Protection Law (VGM)
  • Village Law
  • Water Law
  • Workers' Compensation
  • Zoning

Sign Up for the Mailing List to Be Notified When the Site Is Updated.

  • This field is for validation purposes and should be left unchanged.

Copyright © 2025 New York Appellate Digest, Inc.
Site by CurlyHost | Privacy Policy

UNEXPECTED ABSENCE OF A PROSECUTION WITNESS AFTER ARRESTING OFFICERS TESTIFIED... PLANNING BOARD DID NOT TAKE THE REQUISITE HARD LOOK AT THE IMPACT OF THE PROPOSED...
Scroll to top