Comments on: PLAINTIFF SUED THE DEVELOPER OF PROPERTY ADJACENT TO PLAINTIFF’S BUILDING ALLEGING EXCAVATION WORK CAUSED PLAINTIFF’S BUILDING TO SETTLE AND LEAN; THE CITY ISSUED A STOP-WORK ORDER STEMMING FROM PLAINTIFF’S COMPLAINT; DEFENDANT-DEVELOPER THEN COUNTERCLAIMED ALLEGING PLAINTIFF WAS NEGLIGENT IN NOT MAINTAINING PLAINTIFF’S BUILDING SUCH THAT THE EXCAVATION WORK WOULD NOT DAMAGE IT, RESULTING IN THE STOP-WORK ORDER AND CAUSING THE DEVELOPER PURELY ECONOMIC LOSS OF AT LEAST $16 MILLION; SUPREME COURT LET THE COUNTERCLAIM STAND BUT THE FIRST DEPARTMENT DISMISSED IT; PLAINTIFF DID NOT OWE A DUTY TO THE DEVELOPER AND THE DEVELOPER WAS NOT ENTITLED TO PURELY ECONOMIC DAMAGES (FIRST DEPT). https://www.newyorkappellatedigest.com/2026/06/18/plaintiff-sued-the-developer-of-property-adjacent-to-plaintiffs-building-alleging-excavation-work-caused-plaintiffs-building-to-settle-and-lean-the-city-issued-a-stop-work-order-stemming-from-pla/ Sun, 21 Jun 2026 01:30:30 +0000 hourly 1 https://wordpress.org/?v=7.0.1